by ronfluegge
31. May 2016 13:36
Starting June 1, 2016, monthly audits for compliance with PJM Manual 10 will be performed on all PJM eGADS planned and maintenance outages and deratings.
Manual 10 “Pre-Scheduling Operations” states:
- All planned outages and deratings must be scheduled no less than 30 days prior to the operating day in which the planned outage or derating is to commence. (Section 2.2.1)
- All maintenance outages and deratings must be scheduled no less than 3 days prior to the operating day in which the maintenance outage or derating is to commence. (Section2.3.2)
Please read the document on the PJM eGADS webpage entitled “Scheduled Events (Planned & Maintenance)” at this link for more detailed information: http://www.pjm.com/markets-and-operations/etools/egads.aspx
Keep in mind that compliance is not limited to the most recent eGADS reporting month, but will typically be performed on the existing and most recent Delivery Years.